NewsFlash! Astro Development Sept 7 2018

September 07, 2018

Latest News from the Astro Development for Kilconieron GAA Club



Today we are pleased to report back that:



Phase 1 Groundworks clearing and pipe laying should be completed by Mid September,. 804 has arrived and been fully laid out.


Phase 1 Groundworks tank and percolation area will be completed by Mid September. 


Leveling off of the site almost completed  and handover to the astro development should happen by Mid - Late September


Voluntary donations are coming back to the club, volunteers are pounding the parish highways and byways collecting funds for the development so please give as generously for this community project


Please support our community project and reach out to the many volunteers working on the development within the community.

Thanks again for all your support.